Waldenburgerbahn


Martin Baumann
 

The actual regauging work will be 2021-2022 with the metre gauge due to open 10.12.2022

The last day of 750mm trains will be 05.04.2021


Guerbetaler
 

Am 28.01.2020 um 15:02 schrieb Toma Bacic:
Regauging to 1000 mm?
Yes. And all the renewal work "collected" over the previous years.

Markus, Gürbetal


Toma Bacic
 

Regauging to 1000 mm?

regards
toma


Martin Baumann
 

All trains replaced by buses 28.06.2020-09.08.2020 inclusive due to engineering work

(https://www.blt.ch/unternehmen/news/neubau-wb.html)


Martin Baumann
 

The Waldenburgerbahn have published a (German) pdf at https://www.blt.ch/fileadmin/user_upload/PDF_Content/WB/Linie_19_Ausgabe_1_2018.pdf

detailing the forthcoming gauge change works and other alterations.

The two main points are no trains between Waldenburg and Bubendorf 07.07.2018 to 30.07.2018 inclusive (bus replacement)

A building will be built to display G 3/3 5 and (if the artist impression is accurate) a coach and a van at Thalhaus.

The steam train will run one last time for photographers on 23.09.2018. This train will NOT carry passengers