The new tunnel, which opened on November 2, reduces the line distance by 19.85 metres (65.12 feet)
|
|
Alan McMillan
Spending an undoubtedly huge sum of money to build a tunnel that only shortens the route by less than twenty metres seems a tad profligate to me.
|
|
Guerbetaler
Am 06.01.2021 um 14:59 schrieb Alan McMillan:
Spending an undoubtedly huge sum of money to build a tunnel that onlyPerhaps, before ranting about tunnel meters, maybe you should have asked, WHY the new tunnel was built at all. Now, I tell you, the reason was only to widen the profile. It would have been built, even it would have /added/ 18 m to the distance between Hamburg and Reggio di Calabria. Before a decision was taken, a study was made, if it would be better to enlarge the existing bore or to build a new one. Investment would have been similar but the restriction during the building time weighed out any difference. This was, BTW, similar with the Albula tunnel. Markus, Gürbetal
|
|
George Raymond
Spending an undoubtedly huge sum of money to build a tunnel that only shortens the route by less than twenty metres seems a tad profligate to me.The main rationale was to open the tunnel and thus the route to trains carrying truck trailers that are the standard 4 metres high at the corners. George -- Diese E-Mail wurde von AVG auf Viren geprüft. http://www.avg.com
|
|
Andrew Moglestue
I don't think the objective was ever to shorten the distance, but to make the route usable by freight trains with greater clearances.